Van Ness and Geary Hospital, San Fransisco
This 16 story OSHPD hospital is a fully BIM modeled, design-build fuel oil project to be completed in 2018. Diesel fuel is pumped from six protected class tanks in the basement to the three generators on level 13 and four boilers on level 12. A network of FOS brand PLC controllers is applied to simplify fuel system operation. We are part of an Integrated Project Development Team that has worked on the design for the past 3 years.